S.N |
Name of work |
Contract ID |
Name of Contractor |
Contract Amount |
Date of Agreement |
Date of completion as per Agreement |
Due Date of Completion |
Time Extended based on Original schedule |
Time Elapsed based on revised schedule |
Financial Progress |
Physical Progress |
Progress Status |
Remarks |
Amount |
Percent |
Date |
Percent |
Date |
1 |
Construction of Canal and associated structures from ch.7+300 to 9+000 along Badkapath Main Canal |
BIP/MC/NCB -12/077-79 |
Kankai/Karna J.V., Tokha-6, Kathamandu |
149382060.71 |
2021-04-12 |
2024-10-15 |
|
|
|
|
|
|
|
|
1 |
|
2 |
Construction of Canal and associated structures from ch.9+000 to 14+450 along Badkapath Main Canal |
BIP/MC/NCB -13/077-78 |
Kalika/Bandan Bhagwati/Buddha Himali JV, Baluwatar, Kathmandu |
780077282.08 |
2021-04-12 |
2026-04-13 |
|
|
|
|
|
|
|
|
1 |
|
3 |
Canal lining, drain, related structure and protection work along Badkapath Main Canal, Ch.6+765.25 to Ch7+372.25 |
BIP/MC/NCB-17/079-80 |
Mallarani-K.B.Joint Venture, Pyuthan |
46664625.09 |
2023-07-02 |
2024-06-29 |
|
|
|
|
63 |
|
70 |
|
1 |
|